How much ballast and cement do I need for 1m3?

  • Cement: 230 kg
  • Ballast: 1,380 kg
  • Water: Approximately 150 litres (adjust as needed)
  1. Measure your project area in cubic metres.
  2. Multiply the volume by 230 kg to get the amount of cement needed.
  3. Multiply the volume by 1,380 kg to get the amount of ballast required.
  4. Start with about 150 litres of water per cubic metre, adjusting as necessary.
  • Volume = 2m x 1m x 0.1m = 0.2m3
  • Cement needed = 0.2 x 230 kg = 46 kg
  • Ballast needed = 0.2 x 1,380 kg = 276 kg
  • Water (starting point) = 0.2 x 150 litres = 30 litres
  1. Mix on a clean, flat surface or use a cement mixer for larger jobs.
  2. Add water gradually and mix thoroughly to avoid a too-wet mix.
  3. Only mix as much as you can use within an hour.
  4. Dampen the area before pouring to prevent moisture loss.
  5. Level and smooth the concrete quickly before it starts to set.
  • Use recycled aggregates where possible.
  • Look for cement with a lower carbon footprint.
  • Only mix what you need to reduce waste.
  • Consider alternative materials for smaller projects.

Can I pour concrete in cold weather?